IT method statement

Scope

This Methodology relates to the decommission and re-commission of desk top IT equipment

Process

To successfully carry out this activity the following process should be followed:

  • Ensure full approval for commencing from client's network engineer
  • Check that the machine is logged off the network, switched off and the processor has cooled down
  • Check the machine for labels. Ensure correct convention is used
  • Remove cabling from back of machine including mains, network cable, keyboard, monitor and mouse. Disconnect any other cables from peripherals e.g. External Zip drive, CD-ROM etc. Use bubble bag to contain all cabling
  • The base unit will be wrapped with anti-static bubble roll, placed into the carton, the VDU positioned alongside facing inwards and then the keyboard and cables placed within the carton
  • Use of one Pickfords IT Carton is desirable. Where a second carton is required, it will be labelled accordingly

The re-commissioning of machines occurs as follows:

  • Check positioning of PC relating to desk with IT
  • Check position of PC on desk top - See labelling (left, right or centre)
  • Retrieve base of PC, remove protection and position accordingly
  • Reconnect mains, mouse, keyboard and any other peripherals as appropriate
  • Retrieve monitor, remove protection, place and reconnect
  • If required to do so, patch in network cable to appropriate patch point on floor / wall following the patching plan received from IT
  • Switch on PC observing there is a boot up
  • Where appropriate, Log in using Guest ID, check connectivity to Network - and then log out

case studies

all case studies

Pickfords provides
environmental
solution for the
MOD

Environmental signpost image

Pickfords moves
Birmingham
Children's
Hospital

hospital_small.jpg

Pickfords moves
priceless museum  
exhibits

museum_small.jpg

 

contact your local branch on 0845 130 6559

call me back

enquire online

Get a quote today
for your office move

Get in touch now

download our guide to moving

Download here